Planning Permission Refused: What to Do Next

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 4 min read

Old wooden field gate chained shut to a post, with autumn leaves on the ground

The short answer

If planning permission is refused, you have four options: appeal, apply again with a better scheme, change what you are asking for, or sell or partner on the site. Start with the reasons on the decision notice.

  1. You have six months from the date on the decision notice to appeal.
  2. For applications made on or after 1 April 2026, an appeal cannot rely on new evidence.
  3. If new evidence or a changed design would fix the reasons, apply again instead.
  4. A refused site can still be sold, put into a joint venture or handed to a team to restart.

Planning permission refused on your site? It is a setback, not the end. You can appeal, apply again, change the scheme, or sell or partner on the land. This guide is for owners and developers of sites in England.

Craftex is a London-based property development and construction company. We buy and develop sites across England, and a refused scheme is one kind of problem site we look at. Want a second view? Send us your site and the decision notice.

Why planning permission is refused

Start with the decision notice. The law says it must state the council's full reasons, clearly and precisely. It must also name every local plan policy the council relied on.

Read each reason and sort it into one of two groups.

The two kinds of refusal reason
Kind of reasonWhat it looks likeWhat it usually means
FixableToo tall, too many homes, poor access, a missing reportA changed design or more evidence may answer it
In principleThe council says homes should not go on this land at allYou need a policy argument, or a different route

A refusal can mix both kinds. Count how many reasons a changed scheme would remove. If only one or two would be left, you are closer than it feels.

Appeal, resubmit or change the scheme

You have three planning routes after a refusal. Each suits a different kind of problem.

Three planning routes after a refusal
RouteBest whenWatch out for
AppealThe council applied its own policy wronglyNo new evidence for applications made on or after 1 April 2026
Apply againA changed design or a new report fixes the reasonsA new application means new work and a new wait
Change the schemeThe site suits fewer homes or a different useRun the numbers again before you spend more

Appeal

An appeal goes to the Planning Inspectorate, not the council. For most planning applications you have six months from the date on the decision notice. There is no fee to appeal.

One rule changed this year. For applications made on or after 1 April 2026, most appeals are decided on the papers the council already saw. You cannot add evidence the council did not see.

Our planning appeal guide explains the process step by step.

Apply again

The Planning Inspectorate's own guide is clear on this. If new evidence or a change to the scheme would overcome the reasons, submit a revised application to the council.

Talk to the council first. Our guide to pre-application advice shows how to use that meeting well.

Change the scheme

Sometimes the refusal is telling you something true about the site. A smaller scheme, or a different mix, may get consent. Then test it: planning permission does not mean viable.

How long each route takes

These are the official figures, each with its source.

Official time limits and typical appeal times
StepTimeSource
Time limit to appeal a refusal6 months from the decision noticeGOV.UK
Council's time to decide an application8 weeks, or 13 weeks for major schemesGOV.UK
Appeal decided on written papers18 weeks (median)Planning Inspectorate, October 2026
Appeal with a hearing24 weeks (median)Planning Inspectorate, October 2026
Appeal with an inquiry27 weeks (median)Planning Inspectorate, October 2026

The appeal times are the middle value for all appeal types over the 12 months to September 2026. Your appeal may be faster or slower.

A new application has no fixed total time. It depends on the redesign, the reports and the council.

Selling a site after planning is refused

You can sell a site with a refusal on it. The decision is public, so every serious buyer will read it. What they pay depends on why it was refused and what could still be built.

Do two things before you market it:

  1. Collect the papers. The decision notice, the officer's report, the drawings and every report you paid for.
  2. Write down the fix. One page on which reasons can be answered, and how.

A buyer with its own planning and building team can price the fix. A buyer without one will price the risk.

I’m really pleased with my experience working with Craftex. As a commercial construction firm, they handled everything from start to finish without any unnecessary stress on my side. What impressed me was how they suggested practical ideas that improved the design while also keeping things realistic. The communication was always clear, so I never felt out of the loop. The project ran smoothly, deadlines were met, and the end result is exactly what I was hoping for — a space that feels both functional and modern. It’s not easy finding contractors who are this reliable, but Craftex definitely proved they can be trusted.

Taron Papoyan, Google reviewSee all reviews on Google

When a developer partner helps

A refusal often leaves an owner with a good site, a spent budget and no appetite for a second try. That is where a partner earns its place.

We work with owners in three ways:

  1. We buy it. We buy the site as it is, refusal and all.
  2. We go into a joint venture with you. You put in the land. We bring the team and a new application.
  3. We do it for you. We handle planning, building and sales, and you keep the land.

We take on schemes from about £3M GDV. GDV means the total sale value of the finished homes. We typically take on schemes of £3M to £150M GDV, and larger schemes are welcome.

11,127Homes taken through planning: combined team experience
£228MLand acquired for development: combined team experience
6 monthsTime limit to appeal most refusals (GOV.UK)

Your next step

Note the date on the decision notice today. The six months run from that date. Then decide between the routes with the reasons in front of you.

See how we work with owners on our sell your land page. Or send us your site with the decision notice. We reply within one hour, Monday to Saturday, 8am to 6pm.

This guide is general information, not legal advice. Ask your planning adviser or solicitor about your own case.

What to send us after a refusal

  • The address or postcode and the application reference
  • The decision notice with the reasons for refusal
  • The officer's report, if you have it
  • The drawings and reports from the application
  • Any loan or charge on the site, if there is one

Frequently asked questions

How long do I have to appeal a planning refusal?

For most planning applications in England, six months from the date on the decision notice. Householder appeals have 12 weeks. If an enforcement notice has been served, the time can be as short as 28 days.

Does it cost money to appeal?

The Planning Inspectorate charges no fee for a planning appeal. You still pay your own advisers. Either side can ask for costs if the other has behaved unreasonably.

Can I add new reports to my appeal?

For applications made on or after 1 April 2026, mostly no. The appeal is decided on what the council saw. If a new report or a changed design would solve the reasons, apply again instead.

Will a refusal put buyers off my site?

Buyers will see it, because the decision is public. What matters is why it was refused and what could still be built there.

Will you buy a site with refused planning?

Yes, we look at them. We buy sites with, without, refused or expired planning, from about £3M GDV, across England.

Do these rules apply in Scotland or Wales?

No. This guide covers England only. Scotland, Wales and Northern Ireland have their own planning rules, and we work in England only.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Planning refused on your site?

Send us the site and the decision notice. We reply within one hour, Monday to Saturday, 8am to 6pm.

Reply within 1 hour, Mon–Sat 8am–6pm. Urgent? WhatsApp us for a reply straight away, any day.

WhatsApp us