For developers and investors
Buying Land With Planning Permission: Value, Checks and the Traps
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 9 min read
The short answer
Buying land with planning permission buys certainty on what can be built, not certainty that it makes money. The conditions, the obligations, the time limit and the real build cost decide the price.
- Read the decision notice: full or outline, every condition, and the date the three-year clock started.
- Price the Section 106 and CIL bills: they pass to you with the land.
- Cost the consented scheme at builder level and run it back from the sales values before you bid.
- Land without consent can pay more, if an option or a conditional contract makes the seller share the risk.
Buying land with planning permission gives you certainty on what can be built, not certainty that it makes money. The conditions on the consent, the obligations attached to it, its time limit and the real build cost decide whether the price is right.
We cost and build schemes in London and across the UK. We also find development sites for buyers, so we read consents from the buyer's side.
This guide covers what a consent really gives you and what it is worth. It then sets out the five checks before you bid, and when land without permission is the better deal.
Looking at a consented site now? Send us your deal pack and we will check it before you bid.
Buying land with planning permission: what the consent actually means
"With planning permission" covers very different things. Read the decision notice, not the agent's summary, and settle four points first.
- Full or outline. A full permission is a detailed consent for a defined scheme. An outline permission only agrees the principle. The Planning Portal is clear that outline permission does not act as consent for development to begin.
- Reserved matters. On an outline consent, appearance, access, landscaping, layout and scale may still be open. They must be approved before you can start, and the council decides what it accepts.
- Conditions. Every consent carries them. Pre-commencement conditions ("no development shall take place until…") stop you starting until the council has approved what they ask for.
- The time limit. In England, a full permission must normally be begun within three years of the grant. Outline needs reserved matters applied for within three years, then a start within two years of the last approval.
A consent also runs with the land. In England, it benefits whoever owns the site unless the permission says otherwise. That is good news. The bad news is that the Section 106 obligations and any CIL liability pass to you with it.
Not sure which type of consent you are looking at? Our guide to outline and full planning permission explains each one.
What the consent is worth: work back from the sales value
Here is the trap we see most often. A buyer agrees a price because it "feels right" against other land sales nearby. Then the consented scheme is costed properly, and there is no profit left.
Land value is what is left after everything else is paid. Take the sales value of the finished scheme. Take off the build cost, fees, finance, the planning obligations and a fair profit. What remains is the most you can pay for the land.
Our guide to development appraisal and residual land value shows the full method. For a quick first figure, try our land value calculator.
The illustration below uses made-up round numbers. The scheme sells for £6,000,000 and the buyer wants a 15% profit on sales. The only change between the columns is a higher build cost and higher fees.
| Agent's appraisal | Costed as a builder | |
|---|---|---|
| Sales value | £6,000,000 | £6,000,000 |
| Profit at 15% of sales | £900,000 | £900,000 |
| Build cost | £2,800,000 | £3,400,000 |
| Fees, finance and obligations | £1,100,000 | £1,200,000 |
| What is left for the land | £1,200,000 | £500,000 |
A build cost £600,000 higher, plus £100,000 more in fees, cut the land value from £1,200,000 to £500,000. Pay £1,200,000 on the agent's figures and the profit has gone before you start.
The council will not help you out later. GOV.UK's viability guidance states that the price paid for land is not a relevant justification for failing to accord with the plan. Overpay, and the loss is yours. Before you agree a price, read the real numbers behind a development site for sale.
Five checks before you bid on a consented site
These are the five checks that decide whether a consent makes money. Every one of them can be done before you exchange, and most agents' packs answer none of them.
- Conditions and pre-commencement. List every condition. Mark which must be discharged before a start and what each one costs: surveys, drainage design, materials, construction management plans. Months can go here.
- Section 106 and CIL. The Section 106 agreement can require payments, affordable housing, works or restrictions on use, and it binds anyone who takes title. CIL is charged where the council has a charging schedule, and the landowner is liable unless someone else assumes it. Both are costs of the land, not extras. Our CIL and Section 106 guide explains each.
- Expiry and lawful commencement. Find the grant date and count forward. If the seller says the permission has been "implemented", ask for proof of the works and of the discharged pre-commencement conditions. A start that ignored those conditions may not keep the permission alive.
- Build cost against sales values. Planning drawings are not construction drawings. Nobody has priced structure, services, fire strategy or the finish the sales values assume. Cost the scheme at the level a builder prices, with a contingency. On a housing scheme, our traditional and MMC contractor page covers how the method changes the cost.
- Abnormals, ground and utilities. Contamination, basements, party walls, a power supply upgrade or a sewer diversion can each cost more than the profit on a small site. Test the access, the services and the ground with the right surveys before you commit.
Who should read the consent before you bid
A planning drawing can look buildable and still fail Building Regulations or a fire strategy. Have the decision notice read by a planning consultant and the scheme priced by a builder, both before your bid is final.
A consent is a step, not a guarantee. Our article on why planning permission does not mean a site is viable shows what the five checks have found on real packs.
Buying land without planning permission: when it pays and how to share the risk
Land without planning permission is priced on hope. The seller and the buyer both know a consent could make it worth much more. They also know it might never come.
That hope has a price. Valuers call it hope value: what a buyer pays above the current use for the chance of permission. The upside is that if permission comes, the uplift goes to you, not the seller. You also shape the scheme.
The risks are the mirror image. Refusal can leave you with land worth little more than its current use. The application takes time and money before you know the answer. Lenders are more cautious, so you need more of your own cash.
Three ways to share the planning risk with the seller
Three structures share that risk with the seller.
- A conditional contract. You exchange now, but completion only happens if a satisfactory permission is granted. The seller takes the land off the market while you apply.
- An option. You pay for the right to buy within a set period, often at an agreed price or a discount to market value. You apply for planning during that time.
- A promotion agreement. A promoter wins the planning at its own cost and the land is sold with consent, with the proceeds shared. This is mostly a landowner's tool, but it tells you how the seller's side thinks.
All three live or die on the drafting. What counts as "satisfactory" permission? Who pays for the application? What happens on appeal? Use a solicitor who does land deals. Landowners see the same structures from the other side: our guides to options, promotion agreements and joint ventures and to overage clauses explain them.
Without a consent, the question is the chance of getting one. Check the local plan, the planning history of the site and its neighbours, and the designations. If you already own the land, start with what you can build on your land.
Where consented sites come from in London and the UK
Most consented land reaches buyers by one of three routes. Each one changes how much checking you must do yourself.
- Agents and portals. The widest choice and the most competition. The pack is a sales document: the appraisal uses the seller's build cost and the seller's sales values.
- Auctions. Fast and final. The legal pack is published days before the sale, so the five checks above must be done in that window or not at all.
- Off-market. Sites that never reach the portals. A landowner asks the contractor on a neighbouring job, a consultant knows a consent is about to lapse, a lender has a stalled scheme. Less competition, more work to check.
We are in the industry and active on projects, so off-market deals come to us. We already have deals on the table. If you want to discuss what we have right now, get in touch.
| Agent or portal | Auction | Off-market | |
|---|---|---|---|
| Competition | High | High on the day | Low |
| Time to check | Weeks | Days | Agreed with the seller |
| Who did the appraisal | The seller | Nobody | Nobody |
| Biggest mistake | Bidding on the agent's numbers | Skipping the legal pack | Paying for exclusivity, not value |
Landowners weigh the same routes from their side. If you are the owner, read how to sell land to a developer instead.
Hired Craftex for our conversion project. We had to convert a 600m2 office into 8 apartments. Guys did an excellent job in terms of program efficiency and quality of the finishes which gave us a big upside to exit the project 2 months faster than other competitors’ timelines.
How we check a site before you buy
We work for the buyer on development schemes from £3M to £150M gross development value, in London and across the UK. Our sourcing service finds the deal, including off-market, and then proves the numbers before you commit.
If you are still choosing a site, see how land acquisition for development works step by step. Or see how investors add value to investment property in London through planning and conversion.
On a consented site, our check means:
- reading every condition, the Section 106 and the CIL position, and the date the clock started;
- costing the scheme as a builder would price it, with a contingency;
- running the development appraisal and feasibility study with real costs and telling you the most you should pay;
- highlighting every risk, then negotiating the terms on your behalf.
Our combined team experience includes £225M+ of land acquired and 10,000+ homes through planning. After the purchase, the same team can take the scheme on through planning, design and construction.
What a feasibility study found at Allitsen Road
At Allitsen Road in St John's Wood, the question was what a vacant four-storey corner building in a conservation area could become. We tested options from a four-apartment scheme to a seven-apartment layout using the basement and roof. See the Allitsen Road feasibility study.
We ask serious buyers to have proof of funds, or funding in place, before they approach us. Terms are agreed deal by deal. The checks below are the ones we run first; the full list is in our development site due diligence checklist.
Buying land with planning permission can make money. So can buying without. The difference is whether the price was set from real numbers before you bid. If you are about to commit, send us your deal pack and we will check it with you first.
Before you bid on land with planning permission
- Read the decision notice: full or outline, every condition, the grant date and the time limit.
- List the pre-commencement conditions and what each one costs to discharge.
- Read the Section 106 agreement and check the CIL charging schedule and any liability already assumed.
- Confirm whether a lawful start has been made, with evidence.
- Cost the consented scheme at builder level, with a contingency, and test the sales values.
- Survey the access, the services and the ground for abnormals.
- Run the appraisal again with real costs, then set your maximum price.